Why cables and route in one enquiry?
Because the lengths come from the route. Whoever configures the containment knows how long each cable must be, how many fit in each tier and where they branch off. Doing it in one go avoids cables that are too short, trays that are too full and two suppliers waiting on each other. In our research of 19 November 2026, ChatGPT and Perplexity could not name a supplier that delivers both in one order.
Which cables can you choose?
The configurator uses the diameters of common types to calculate the fill ratio per run.
| Cable | Use | Diameter (mm) |
|---|---|---|
| Cat6A U/FTP | copper, 10 Gbit/s | 7.5 |
| Cat6A S/FTP | copper, screened | 8.0 |
| OM4 patch | multimode fibre | 2.0 |
| OM4 trunk MPO-12 | fibre, pre-terminated | 6.0 |
| OS2 trunk MPO-12 | singlemode fibre | 6.0 |
| 3G2.5 | power | 10.5 |
| 5G6 | power | 16.0 |
| 5G16 | power | 22.0 |
Diameters are typical values (indicative); the cable manufacturer gives the exact size.
How does cable assembly work in the configurator?
Per line you choose the cable type, length, quantity and the connectors at both ends, with an optional label. Each line becomes one bill of materials line, so the supplier knows exactly what to make. Power and data in one run without a divider show a red status: the enquiry still goes through, with a clear warning.
- Cable type, length in metres and quantity
- Connector A and connector B, for example RJ45 or MPO
- Label per cable or bundle
- Fill ratio per run: up to 40% fine, up to 60% full, above that over-filled (rule of thumb)
Frequently asked questions
Can Cat6A and fibre share the same containment?
Yes, fibre is immune to interference. Protect fibre from kinking and crushing by heavy cables, for example with its own tier or raceway.
Do power and data need to be segregated?
Yes, with a divider or in separate containment, following the applicable IEC and national standards. The configurator warns when they are not.
What is an MPO trunk?
A pre-terminated fibre cable with MPO connectors, for example 12 fibres, laid quickly between racks in data centres.