Strutconfigurator
Locations

Roof support blocks for strut: flat roof spacing and wind

Updated 5 min readBy Ismail Yeşilay · Strutconfigurator

Short answer

Roof support blocks carry strut channel on a flat roof without penetrating the membrane. A 200×200 mm rubber block with 41 mm channel on top is the basis for cable routes, condenser units and pipework. Have a structural engineer check roof capacity and wind uplift. In Strutconfigurator you set the height and length of the roof support run.

Roof support blocks let you run cable routes, condenser units and pipework across a flat roof without a single penetration. No penetrations means no leak risk and no call-back to the roofer. The support system still has to cope with wind, sun and standing water, and the roof has to carry the load. On UK sites you will hear them called strut feet or Unistrut feet. This guide covers the build-up, the spacing and what to agree with the structural engineer and the roofer.

A roof support block is a loose foot, usually recycled rubber or plastic, that holds strut channel in or on top of it. The weight of the system keeps it in place. The configurator’s default is a 200×200 mm rubber block with 41 mm channel.

What are roof support blocks used for?

Use Build-up Watch out for
Cable route, for example from PV arrays to the inverter Blocks with a 41×41 cross member, lidded tray UV, water in the tray, lid security in wind
Condenser or air handling unit Two or more cross members on blocks, or a frame Vibration, maintenance access around the unit
Refrigerant or condensate pipework Block with channel and pipe clips Expansion along the run
Cable ladder between plant Blocks with an upright and cross member, like a low H-frame Height above the roof, wind

Overview, indicative. More applications in solar and roofs.

How is a roof support built up?

From the bottom up:

  1. Protection layer on the membrane.
  2. Support block, 200×200 mm by default in the configurator.
  3. Strut channel in or on the block, usually 41×41 hot-dip galvanised.
  4. An upright in strut, where the route needs to sit higher, with a cross member as on an H-frame.
  5. Tray, ladder or pipe clips on the cross member, held with clamps on channel nuts.

For condenser units, fit anti-vibration mounts between the unit and the cross members, so vibration does not travel through the frame into the roof deck. Keep clear the service space the unit manufacturer specifies.

How far apart should the blocks be?

The channel between two blocks works as a beam, so use its load table:

Span 41×41 slotted, max. (kN) 41×41 slotted, at L/200 (kN)
1,000 mm 4.01 n/g
1,500 mm 2.68 2.13
2,000 mm 2.00 1.20

Manufacturer data [1]: total uniformly distributed load on a simply supported beam. Indicative; the manufacturer confirms. n/g = not given; up to 1,000 mm deflection stays within L/200.

For light cable routes that comes to one block every 1.5 to 2 m (rule of thumb, indicative). Add a block at each bend, branch and end.

Check the bearing pressure too. A 200×200 mm block covers 0.04 m². Carrying 0.5 kN, it presses 12.5 kN/m² onto the membrane and the insulation below (worked example). Compare that with the compressive strength on the insulation’s datasheet. If it is too close, use a larger block or more blocks.

How do you deal with wind uplift?

Wind pulls on anything that stands above the roof, and suction peaks at edges and corners. A structural engineer calculates wind actions to BS EN 1991-1-4 with the UK National Annex [2]. That shows whether self-weight is enough or whether ballast or a fixing is needed.

Three design rules of thumb (indicative):

  • Stay out of the edge and corner zones where you can.
  • Keep it low. Tray 150 mm above the roof catches less wind than ladder at 600 mm.
  • Lid the tray and secure the lids with cover clips.

Where the route serves a PV array, agree it with the array designer, who will already be working to the wind loads for the panels.

How do you protect the roof membrane?

  • Always a protection layer. A rubber or protection mat under each block stops it pressing into the membrane.
  • Check compatibility. Some rubbers and plastics react with bitumen or PVC single-ply. Get the roofer’s or membrane manufacturer’s agreement.
  • Let water run. Do not set blocks across the fall where they dam water, and keep outlets and overflows clear.
  • Inspect yearly. Check that blocks have not walked and that the protection layer is intact.

Does a steel roof frame need lightning protection?

Metal on the roof belongs in the lightning protection design to BS EN 62305 [3]. There are two routes: bond the frame to the lightning protection system, or keep a separation distance. The lightning protection designer decides which applies. Settle it before the route goes down.

Which finish suits a roof?

Hot-dip galvanised is the standard outdoors, with 45 to 55 µm of zinc on strut channel [4]. Near the coast or in aggressive industrial air, use stainless 316. The choice is explained in pre-galvanised vs hot-dip galvanised vs stainless.

Allow for expansion. Steel grows by about 0.012 mm per metre per degree [5]. A 6 m length that sees 60 degrees between a winter night and summer sun grows 4.3 mm (worked example). Let long runs slide in the blocks and use slotted couplers.

How does the configurator handle roof supports?

In the roof supports module you set the run length and the build-up height. The configurator puts the 200×200 mm rubber blocks, channel and fixings into the bill of materials and cutting list. Choose “on the roof” in the first step and it proposes hot-dip galvanised.

Where do these figures come from?

  1. Atkore UK, P1000T product page, Beam Loading table. Accessed 19-11-2026. https://www.atkore.com/en-gb/products/metal-framing-and-fittings/P1000T
  2. BS EN 1991-1-4, Eurocode 1: Actions on structures, Part 1-4: General actions, wind actions, with the UK National Annex.
  3. BS EN 62305, Protection against lightning, Parts 1 to 4.
  4. Eurostrut, hot-dip galvanised strut channel, 45 to 55 µm coating. Accessed 19-11-2026. https://eurostrut.com/montageprofiel-41x41mm-met-gaten-3m-tv/ES1000THDG3M
  5. Coefficient of thermal expansion of steel, about 12 × 10⁻⁶ per kelvin: rule of thumb, indicative.

Frequently asked questions

How far apart should roof support blocks be?

That follows from the load per metre and the span of the channel. With slotted 41x41 held to L/200 deflection, light cable routes typically work out at one block every 1.5 to 2 m (rule of thumb, indicative), plus an extra block at every bend and branch.

Do roof support blocks need fixing against wind?

It depends on building height, position on the roof and how much area catches the wind. Suction is highest at edges and corners. A structural engineer uses BS EN 1991-1-4 with the UK National Annex to decide whether self-weight is enough or ballast or fixing is needed.

Can a support block sit straight on the membrane?

Lay a protection layer underneath, such as a rubber or protection mat, and ask the roofer or membrane manufacturer to confirm compatibility. Some rubbers and plastics react with bitumen or PVC membranes. Keep drainage paths clear as well.

What are Unistrut feet?

On UK sites the term covers two things: steel base plates that fix an upright to a floor, and loose roof support blocks that carry channel on a flat roof without fixings. This page is about the second; base plates are covered in the H-frame guide.

Next step

See your own range in 3D.

In 30 minutes we show how your installers configure, what arrives on your side and what the client version on your range involves.

Manufacturer or wholesaler

Book a demo with Ismail

You see the configurator in your own brand and we discuss your range, systems and markets.

Reply from Ismail within one working day

Installer

Configure for free

A trapeze, frame or tray with cables in a few minutes, with a bill of materials and drawing.

Enquiry goes to a supplier · reply within one working day